Self-build home: Prepare a concept design
Introduction.
In this stage, we attribute design activities to ‘designers’. These may be architects and engineers, a design and build contractor, or a kit house supplier. If a kit house supplier is only supplying the house itself, additional design consultants may be required.
Concept design is the first design stage. Some designers will differentiate between 'concept design' and 'scheme design'. In this case, the 'concept' is the initial design idea (or outline design), whereas the 'scheme' develops the concept, taking on board more functional and practical considerations.
It may be necessary for designers to undertake site surveys and other site appraisals before starting the concept design, for example, digging trial pits before designing foundations.
Design is an iterative and collaborative process, it requires close involvement of all those with an interest in the completed home. This is important not only to ensure a suitable design is developed, but also to make certain that everyone has ‘bought into’ the design and it is not just one person’s vision.
Developing the brief.
It is likely that the project brief will continue to develop as the concept design is prepared. It is important that these developing requirements are written down so there is a record of what has been agreed. Development of the brief might include:
- Preferred style and materials.
- Requirement for spaces to be open plan or enclosed.
- Ability to operate parts of the building separately (for example an office, children’s areas or guest rooms).
- Sound insulation and sound absorption requirements.
- Provision of en-suite or shared bathrooms, dressing rooms and so on.
- Accessibility requirements for people with disabilities or impaired mobility.
- Access to and views of gardens and the surrounding landscape.
- Entry spaces and reception spaces.
- Fireplaces, wood burning stoves and so on.
- Hard v soft floor coverings.
- Security, intruder alarms, cctv, door and gate entry systems and post facilities.
- Audio visual, ICT, entertainment and other equipment requirements.
- Specialist requirements for finishes, fixtures and fittings.
- Orientation in relation to the sun, prevailing winds and views.
- Natural lighting.
- Artificial lighting (general and feature) and controls.
- Comfort conditions (radiant temperature, air temperature, natural and mechanical ventilation and so on).
- Storage requirements and utility rooms.
- Internal and external waste storage and collection.
- The possibility of including enabling works for future extensions.
- Galleries and balconies.
- External landscaping such as; planting, seating areas, drainage, sprinklers and taps, lighting and power, paths, screens, fences, walls, shading and so on.
Developing the concept design.
The concept design should develop to include:
- A site plan, including; access, car parking, hard surfaces, landscape, water features, art and so on.
- Floor plans, sections and elevations.
- Analysis of the relationships between related functions.
- Building services strategy (heating, ventilation, electrical supply, lighting and so on).
- Outline specification describing the main materials and workmanship required.
- Schedules of accommodation.
- A strategy for obtaining planning permission.
- Procurement strategy.
- Programme, construction methodology and logistics.
- Approximate quantities of the main materials proposed.
- A cost plan (including site preliminaries).
This information should be co-ordinated and issued at the end of the stage for comment or approval before the project proceeds to detailed design or a planning application is submitted.
The brief should be frozen at the end of the concept design stage and any subsequent changes that materially alter the cost should be carefully considered by the self builder for approval or rejection.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February